WHX 2026: Medical Imaging Demo Compliance Checklist
WHX 2026 at the Dubai Exhibition Centre (DEC) and the DWTC Labs represents the highest-stakes cycle for exhibitors. For teams running imaging demonstrations, medical imaging exhibition compliance Dubai is the operational linchpin: WHX runs 9–12 February 2026 at DEC while WHX Labs (MedLab track) runs 10–13 February at DWTC, creating a combined mega-cycle with concentrated technical demand.
Why WHX 2026 Is High‑Risk For Imaging Equipment Demos — medical imaging exhibition compliance Dubai
Three factors make WHX 2026 uniquely high-risk for large imaging demos:
- Scale: Organisers project ~4,300–4,800+ exhibitors and ~235,000+ professional visits — peak marshalling congestion and inspection bottlenecks.
- Venue split and move to DEC: The show moves major activity to the DEC while WHX Labs continues at DWTC (10–13 Feb). This split-site model forces many exhibitors to interface with two marshalling areas and different technical rules, increasing handover points and delays.
- Concentrated technical demand: Heavy imaging machines require specialised customs, power, floor protection and crane windows; teams that don’t plan for marshalling slots and split-site transfers risk multi-hour on-site delays.
Critical Technical & Regulatory Requirements Exhibitors Must Nail — medical imaging exhibition compliance Dubai
Exhibitors must treat compliance as a project. Key items and timing:
Dates & deadlines
- Event: 9–12 Feb 2026 at DEC; WHX Labs: 10–13 Feb at DWTC.
- RAMS/shop drawings: Typically due 3–6 weeks before build-up (submit in English as venue requires).
Customs & device import
- Temporary import via MOHAP permits or an ATA Carnet with serial-number matching for each demo device — mismatches cause customs holds and MOHAP refusals.
Venue structural & fire rules
- DEC/DWTC hall floor loading: typically ~1,500–2,000 kg/m² with higher-rated zones by prior approval.
- Point‑loads (machine feet/tyres) must be spread with engineered spreader plates and venue sign-off.
- Dubai Civil Defence (DCD) requires fire‑rating certificates for booth finishes; powered demos may need segregation or suppression.
Power, heavy lift & hazardous items
- Order three‑phase/24‑hour IEC power through the venue; connectors and phased supply must be specified. Late power orders are often subject to 20–50% surcharges or availability limits.
- Heavy‑lift/crane windows are limited and must be pre‑booked — plan early and reserve slots for transfer between DEC and DWTC if required.
- Declare hazardous items and submit the relevant SDS, hazardous‑item declarations and transport paperwork within venue timelines.
The Five Most Common Failures (and Their Real Costs) — medical imaging exhibition compliance Dubai
- Customs / MOHAP holds: ATA Carnet serial mismatches or missing temporary‑import documents. Consequence: machine detention and missed demos; remediation often requires customs agents and can cost last‑minute premiums of 10–30%.
- Incorrect power/inrush: Wrong phase, connector or failure to manage inrush current trips breakers. Consequence: demo downtime and emergency electricians; expect overtime premiums and tiered venue surcharges.
- Un‑approved point loads: Machines placed on standard flooring without an engineered spreader plate cause urgent structural fixes. Emergency spreader plate engineering and install can add significant labour and third‑party fees.
- Missed heavy‑lift windows: Crane re‑booking or emergency lifts attract third‑party premiums. Market data shows last‑minute heavy‑lift rates often carry 10–30%+ premiums over contracted rates.
- Late technical orders & venue surcharges: Late RAMS or power orders can trigger 20–50% venue surcharges; overtime and performance‑bond deductions are common for delayed sign‑offs.
Burdak’s Factory‑First Fix: In‑House Fabrication, CNC Joinery & Mock‑Up Guarantees — medical imaging exhibition compliance Dubai
We eliminate last‑mile risk by moving critical work into our factory. Core services we deliver:
- Pre‑engineered spreader plates & reinforced plinths: We design and manufacture plates (CNC, steel/structural grade) sized to device feet, with structural calculations and engineer’s stamp for venue sign‑off.
- Inrush/current sequencing tests: Full electrical commissioning and sequencing tests in our facility to validate start‑up currents and specify soft‑start or sequencer hardware prior to site.
- DWG/shop & RAMS packages: We compile DWG/shop drawings, structural calcs, RAMS PDFs and fire test certificates ready for DEC/DWTC submission.
- Full‑scale pre‑assembly mock‑ups: Factory mock‑ups reduce site build time by 40–60%, reduce customs inspection failures and speed organiser sign‑offs.
- Sequenced, labelled deliveries: We manage crate sequencing to match marshalling slots so machines arrive exactly when required — reducing on‑site labour and third‑party overtime.
Measured benefits: fewer on‑site hours, reduced emergency third‑party premiums, and faster DCD/venue approvals thanks to engineer‑stamped packs and verified mock‑ups.
8‑Week Pre‑Show Checklist & Timeline (Actionable) — medical imaging exhibition compliance Dubai
Below is a week‑by‑week actionable timeline to hit WHX 2026 deadlines.
- Week 8: Finalise BOQ and material passport. Start MOHAP / ATA Carnet checks; collect serial numbers for devices.
- Week 7: Commission structural calcs for spreader plates and plinths. Begin RAMS drafting.
- Week 6: Submit RAMS and shop/DWG drawings if possible (target 3–6 weeks prior).
- Week 5: Order venue power (three‑phase/24‑hour IEC) and reserve heavy‑lift/crane windows. Book marshalling slots and crate sequencing.
- Week 4: Factory mock‑up and CNC joinery pre‑assembly. Perform inrush/current sequencing tests and adjust hardware as necessary.
- Week 3: Compile final submission pack: DWG/shop files, RAMS PDF, fire test certificates, engineer’s stamp (structural calcs), SDS and ATA/MOHAP docs.
- Week 2: Confirm crate labels, courier bookings, and marshalling delivery slots. Reconfirm heavy‑lift and electrical arrival windows.
- Week 1–0: Deliver staged crates per marshalling schedule; on‑site assembly teams use factory labels and documented sequencing to minimise time in the hall. Perform final DCD / venue sign‑offs.
File types and deliverables to prepare: DWG/shop drawings (layout & structural), RAMS PDF, fire test certificates PDF, engineer’s stamp (signed PDF), SDS sheets, ATA Carnet pages or MOHAP permits.
FAQ — medical imaging exhibition compliance Dubai
Q: When must RAMS and shop drawings be submitted?
A: RAMS and engineered shop/DWG drawings are typically required 3–6 weeks before build‑up. Submit earlier where possible to avoid review delays.
Q: Do I need an ATA Carnet or MOHAP paperwork?
A: Yes. For demo medical devices you need temporary‑import documentation. An ATA Carnet with serial‑number matching or MOHAP temporary import permits are mandatory to avoid customs holds.
Q: What are the risks of ordering power late?
A: Late power or last‑minute changes can lead to 20–50% surcharges, limited availability, and potential impact on demo operation due to incorrect connectors or inrush issues.
Q: How does Burdak reduce on‑site risk?
A: We pre‑engineer spreader plates, perform factory inrush tests, deliver full‑scale mock‑ups and provide DWG/RAMS packs so venues and DCD sign off earlier and on‑site hours are reduced.
For WHX 2026, treat compliance as a technical project. We help customers control risk with factory‑first engineering, mock‑ups and sequenced delivery that convert the complicated WHX logistics into a reliable, signable plan.